«

»

Sep 21

Weekly Update September 21, 2020

PSE&G Former Harrison MGP Site: Weekly Project Update – Week of 9/21/20

The PSE&G site remediation group and its environmental contractor, Sevenson Environmental Services, Inc., are conducting activities to remediate soils at the Harrison former MGP site. Work began in July 2020 and is expected to end by December 2022. Work is being performed in two phases.

The sitewide remediation project includes removing approximately the top 7 feet of soil below ground surface in preparation for treatment of deeper impacted soils through In Situ Solidification and Stabilization (ISS). ISS involves mixing impacted soils in place, below ground, with stabilizing agents such as Portland cement and blast furnace slag. Impacted soils in the vicinity of the active Meter and Regulating (M&R) Station and its infrastructure will remain in place but contained through installation of below ground slurry walls. 

These updates are being issued weekly throughout the duration of the project to provide a review of key activities performed at the site over the past week as well as a look ahead to the next week’s anticipated activities. They are also posted to the project website: www.HarrisonMGP.com.  If you have any questions or concerns about the project, please: visit our website at www.harrisonmgp.com; call the PSE&G Harrison Project Information Line at (855) 356-2383; or email us at comments@harrisonMGP.com.

PLEASE TAKE NOTE:  
Hyatt Line Gas Main:  
Work to install the new Hyatt Line Gas Main, which is not related to the MGP remediation, continues at the PSE&G Harrison Site. 

  • 10 hour days, 6 days per week are anticipated during the maximum 14-day-long gas outage, which is scheduled from September 21st through October 3rd.  All monitoring and mitigation measures will be maintained, including dust and odor controls. See Figure 2 below showing the flow of trucks working on this project on the PSE&G site.

Anticipated Work for the Week of September 21 – September 25

Remediation Activities – (See Figure 1 below and on the website)

  • Continue removing debris from ISS Pilot Area and
  • Begin ISS in northern area of the work site.
  • Transport excavated soil from the site by trucks for disposal or reuse at a New Jersey licensed facility.
  • Continue pre-trenching and subsurface demolition to cut and cap underground utilities and remove old infrastructure.  This work will generate sounds from breaking of concrete and removal of metal piping and other materials. 

Continue Monitoring & Mitigation Measures

  • Apply dust suppression and odor controls, as needed, during remediation activities. 
  • Continue vibration monitoring between remedial work and the nearest onsite buildings.
  • Continue to perform perimeter air monitoring when soil disturbance work is in progress. The majority of air monitors are located each day based on location(s) or work being performed. There is one stationary air monitor by the Laboratory Air Intake, which will remain in place for as long as the laboratory is in use.
  • Maintain site security 24 hours a day, 7 days a week.

NOTE:  Odors associated with some constituents can often be detected at levels that are well below what would be considered a health concern and often below what can be detected by an air monitoring instrument. The MGP project continues to:

  • Apply vapor mitigation sprays in the excavation area.
  • Apply odor suppressing foams in the excavation area and in the trucks while being loaded.
  • Use odor suppressing foams more frequently and in greater amounts.
  • Cover project soil piles with plastic when work is completed.
  • Perform daily odor assessment walks around the MGP remediation work areas to determine if and at what levels odors may be detected beyond the work area fenceline. 

Other control measures, including water mist and sand, will be used as needed to control potential dust and odors during excavation and non-work periods, including evenings and weekends. The MGP project performs continuous air monitoring during working hours around the site, including monitoring stations by the welding shop, laboratory, and gym buildings. Confirmatory air samples are taken weekly and all results have been below our action levels. 

Continue Site Preparation Activities

  • Relocate Soil Handling Materials (not associated with MGP Remediation) and onsite equipment not involved in remediation. 
  • Complete temporary wastewater treatment facility to control groundwater and surface water accumulations during work activities. Treated water will be discharged in accordance with a permit issued by the Passaic Valley Sewerage Commission. 
  • Continue to construct batch plants for ISS materials.
  • Maintain soil and sediment erosion controls. 
  • Install temporary fencing around active work areas.

Work Completed September 14 – September 18

Remediation Activities

  • Held drill rig training using water to simulate ISS production.
  • Excavated soil within the area marked Pilot Study Area and in the northeast section of the remediation to remove approximately the top 7 feet of soil below ground surface in preparation for ISS.
  • Transported excavated soil from the site by trucks for disposal or reuse at a New Jersey licensed facility.
  • Continued pre-trenching and subsurface demolition to cut and cap underground utilities and remove old infrastructure. 

Monitoring & Mitigation Measures

  • Applied dust suppression and odor controls during pre-trenching activities. 
  • Continued vibration monitoring between remedial work and the nearest onsite buildings.
  • Continued to perform perimeter air monitoring when soil disturbance work is in progress. 
  • Maintained site security 24 hours a day, 7 days a week.

Site Preparation Activities

  • Installed waste water treatment plant discharge line.
  • Relocated onsite equipment not involved in remediation. 
  • Mobilized remediation equipment and personnel to the project site as needed.
  • Performed soft digging to identify underground utilities around the work area perimeter. 
  • Established protection around utilities.
  • Installed additional soil and sediment erosion controls. 
  • Installed temporary fencing around active work areas.
  • Completed construction of drill rigs.
  • Continued construction of a temporary wastewater treatment facility. 
  • Pre-trenched and conducted subsurface demolition to cut and cap underground utilities and remove remnants of old infrastructure.  


Community Outreach 

  • Responded to odor concerns raised by onsite personnel. 
  • Provided information about the Hyatt Line maintenance program on Cape May Street to property managers of Vermella, Steel Works, and Cobalt Lofts facilities. This work is not related to the MGP-site remediation.
  • Issued 7th weekly update email to representatives of the Town of Harrison, Hudson County Regional Health Commission, and property managers of Vermella, Steel Works, and Cobalt Lofts apartment complexes, as well as the owners of Joia Restaurant and officials of Amtrak.
  • Held 4th weekly call between remediation project team and PSE&G site management for improved communication and coordination.
  • A virtual Community Information Session is being planned and will take place in the coming weeks. This will be an opportunity to see and hear more about the project and to ask questions of the project team. More information on when and how to access this virtual event will be available soon.

The PSE&G remediation project team is committed to: conducting work safely on the job site; minimizing impacts from the project to those outside of the project area; keeping PSE&G non-project personnel, the local community, elected officials, and all interested parties informed of our progress; and enhancing the property’s continued productive use. The team will follow the guidelines and directives issued by the New Jersey Department of Health, the CDC and the Occupational Health and Safety Administration, as applicable, for maintaining a clean, safe and healthy work environment. PSE&G personnel and contractors are required to participate in social distancing and wear appropriate gloves and face coverings during all work activities

All work is being performed in accordance with the guidance and regulations of the New Jersey Department of Environmental Protection (NJDEP), and under the oversight of the Licensed Site Remediation Professional (LSRP) of record. 

FIGURE 1

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>