Adm1n

Author's details

Date registered: January 3, 2018

Latest posts

  1. Update April 2, 2019 — April 3, 2019
  2. Update March 18, 2019 — March 18, 2019
  3. Update March 4, 2019 — March 4, 2019
  4. Update February 18, 2019 — February 15, 2019
  5. Update February 4, 2019 — February 5, 2019

Author's posts listings

Apr 03

Update April 2, 2019

PSE&G Former Harrison MGP Site – April 2, 2019   The PSE&G site remediation group and its environmental consultant, PS&S, have completed the onsite pre-design work that began in January at the Harrison former Manufactured Gas Plant (MGP) site.   The next phase of remediation is expected to begin in 4th Quarter 2019. Before any …

Continue reading »

Mar 18

Update March 18, 2019

PSE&G Former Harrison MGP Site – March 18, 2019   The PSE&G site remediation group and its environmental consultant, PS&S, are performing onsite pre-design work at the Harrison former Manufactured Gas Plant (MGP) site as part of planning for the next phase of remediation, which is expected to begin in 4th Quarter 2019.   The …

Continue reading »

Mar 04

Update March 4, 2019

PSE&G Former Harrison MGP Site – March 4, 2019   The PSE&G site remediation group and its environmental consultant, PS&S, are performing onsite pre-design work at the Harrison former Manufactured Gas Plant (MGP) site as part of planning for the next phase of remediation, which is expected to begin in 4th Quarter 2019.   The …

Continue reading »

Feb 15

Update February 18, 2019

PSE&G Former Harrison MGP Site – Week of February 18, 2019   NOTE: On Monday, February 18 and Tuesday, February 19, contractors working on behalf of the PSE&G site remediation group will be performing soil boring advancement and soil sample collection within the site’s internal access road that runs north-south. Drilling will be phased to …

Continue reading »

Feb 05

Update February 4, 2019

PSE&G Former Harrison MGP Site – February 4, 2019   The PSE&G site remediation group and its environmental consultant, PS&S, are performing onsite pre-design work at the Harrison former Manufactured Gas Plant (MGP) site as part of planning for the next phase of remediation, which is expected to begin in 4th Quarter 2019.   The …

Continue reading »

Jan 25

Update January 21, 2019

PSE&G Former Harrison MGP Site – January 21, 2019   The PSE&G site remediation group and its environmental consultant, PS&S, are performing onsite pre-design work at the Harrison former Manufactured Gas Plant (MGP) site as part of planning for the next phase of remediation, which is expected to begin in 4th Quarter 2019.   The …

Continue reading »

Jan 09

Update January 10, 2019

PSE&G Former Harrison MGP Site – January 10, 2019 The PSE&G site remediation group and its environmental consultant, PS&S, are performing onsite pre-design work at the Harrison former Manufactured Gas Plant (MGP) site as part of planning for the next phase of remediation, which is expected to begin in 4th Quarter 2019. The current activities …

Continue reading »

Nov 19

Weekly Update 11-19-18

Work to be performed: November 19-November 21, 2018 Paving by the southern gate entrance. Demobilize remaining equipment from site. Remove construction debris for proper disposal. Complete onsite security. Work will be completed before the Thanksgiving holiday.   Work performed: November 12-November 16, 2018 Compacted, backfilled and restored site. Demobilized project trailers. Demobilized equipment from the …

Continue reading »

Nov 12

Weekly Update 11-12-18

Work to be performed: November 12-November 16, 2018 Continue to compact, backfill and restore site. Demobilize project trailers. Decontaminate and demobilize equipment from the site. Complete decontamination of batch plant. Mobilize crane to site for batch plant demobilization. Remove perimeter fencing. Complete vibration monitoring. Maintain onsite security for after hours and weekends.   Work performed: …

Continue reading »

Nov 12

Weekly Update 11-5-18

Work to be performed: November 5-November 9, 2018 Continue to remove materials and transport them for proper disposal. Continue to import clean backfill and restore areas where ISS work has been completed. Begin decontamination of equipment and demobilization. Begin preparation of batch plant for demobilization. Continue vibration monitoring. Conduct continuous air monitoring while soil disturbance …

Continue reading »

Older posts «