Weekly Update 11-19-18

Work to be performed: November 19-November 21, 2018

  • Paving by the southern gate entrance.
  • Demobilize remaining equipment from site.
  • Remove construction debris for proper disposal.
  • Complete onsite security.
  • Work will be completed before the Thanksgiving holiday.

 

Work performed: November 12-November 16, 2018

  • Compacted, backfilled and restored site.
  • Demobilized project trailers.
  • Demobilized equipment from the site.
  • Demobilized batch plant.
  • Removed perimeter fencing.
  • Completed vibration monitoring.
  • Maintained onsite security for after hours and weekends.