Oct 29

Weekly Update 10-29-18

The PSE&G site remediation group and its environmental contractor, Panther Technologies, Inc., are nearing the end of their activities related to the current remediation phase of the Harrison former Manufactured Gas Plant (MGP) site.  This work began mid-January 2018 and is expected to be completed late November 2018. Work hours are extended to until approximately 5 p.m. for the duration of the project.

We thank you for your continued patience.

The work is being performed in accordance with the guidance and regulations of the New Jersey Department of Environmental Protection (NJDEP), and under the oversight of the Licensed Site Remediation Professional (LSRP) of record. PSE&G is also working in close coordination with the Town of Harrison.

If you have any questions or concerns about the project, please: visit our website at www.harrisonmgp.com; call the PSE&G Harrison Project Information Line at (855) 356-2383; or email us at comments@harrisonMGP.com.

Work to be performed: October 29-November 2, 2018

  • Continue to receive deliveries of materials.
  • Continue ISS treatment of soils.
  • Continue to remove materials and transport them for proper disposal.
  • Continue to import clean backfill and restore areas where ISS work has been completed.
  • Continue to perform localized construction dewatering activities and operate the groundwater treatment system. The treated water is discharged to PVSC.
  • Continue efforts to mitigate odors naturally associated with MGP materials, including foaming, running a permanent odor-neutralizing perimeter drip system, use of BioSolve Pinkwater as an additional vapor suppression product and daily odor assessment patrols two times a day.
  • Continue water misting to reduce dust.
  • Continue vibration monitoring.
  • Conduct continuous air monitoring while soil disturbance activities are underway.
  • Maintain onsite security for after hours and weekends.
  • Offsite trailer is available for use by laboratory personnel, as they deem necessary.
  • Parking spaces immediately adjacent to the project site are closed off for the duration of the project.

Work performed: October 22-October 26, 2018

  • Continued excavation and ISS treatment.
  • Continued to receive deliveries of materials.
  • Continued to remove materials for proper disposal.
  • Continued to perform localized construction dewatering activities and operate the groundwater treatment system. The treated water is discharged to PVSC.
  • Continued efforts to mitigate odors naturally associated with MGP materials, including foaming, running a permanent odor-neutralizing perimeter drip system, use of BioSolve Pinkwater as an additional vapor suppression product and conducting daily odor assessment patrols.
  • Continued water misting to reduce dust.
  • Continued vibration monitoring.
  • Conducted continuous air monitoring while soil disturbance activities were underway.
  • Maintained onsite security for after hours and weekends.

Community Outreach 

  • Distributed 40th weekly update to PSE&G managers for broader distribution and Harrison elected and health officials.
  • Posted weekly update and photos on Harrison MGP project website: www.harrisonmgp.com.