Feb 26

Weekly Update 2-26-18

Work to be performed: February 26-March 2, 2018

  • Continue installation of groundwater treatment system.
  • Continue to receive deliveries of equipment and materials to the project site.
  • Continue to break up underground foundations and structures along the perimeter of the work site area, and remove materials for proper disposal.
  • Continue excavation of soils along the project perimeter, down to 4 feet.
  • Continue to perform localized construction dewatering activities.
  • Conduct vibration monitoring.
  • Conduct continuous air monitoring at project site perimeter while soil disturbance activities are underway.
  • Maintain onsite security for after hours and weekends.
  • Post validated air monitoring results to website.

 

Work performed: February 19-23, 2018

  • No work was performed February 19 for Presidents’ Day.
  • Continued installation of groundwater treatment system.
  • Continued to receive deliveries of equipment and materials to the project site.
  • Continued to cut and cap utilities entering the work site area.
  • Conducted vibration monitoring.
  • Conducted continuous air monitoring at project site perimeter while soil disturbance activities were underway.
  • Established onsite security for after hours and weekends.