Weekly Update 2-19-18

Work to be performed: February 20-23, 2018

 

No work was performed on Monday, February 19 in observance of the Presidents Day holiday.

 

  • Continue installation of groundwater treatment system.
  • Continue to receive deliveries of equipment and materials to the project site.
  • Continue to break up underground foundations and structures along the perimeter of the work site area, and remove materials for proper disposal.
  • Begin excavation of soils along the project perimeter, down to 10 feet.
  • Continue to perform localized construction dewatering activities.
  • Conduct vibration monitoring.
  • Conduct continuous air monitoring at project site perimeter while soil disturbance activities are underway.
  • Maintain onsite security for after hours and weekends.
  • Post first validated air monitoring results and air monitoring background results to website.

 

Work performed: February 12-16, 2018

 

  • Began installation of groundwater treatment system.
  • Continued to receive deliveries of equipment and materials to the project site.
  • Continued to cut and cap utilities entering the work site area.
  • Conducted vibration monitoring.
  • Conducted continuous air monitoring at project site perimeter while soil disturbance activities were underway.
  • Established onsite security for after hours and weekends.