«

»

Feb 12

Weekly Update 2-12-18

Work to be performed: February 12-16, 2018

 

  • Continue to receive deliveries of equipment and materials to the project site.
  • Continue to cut and cap utilities entering the work site area.
  • Break up underground foundations and structures along the perimeter of the work site area, and remove materials for proper disposal.
  • Perform localized construction dewatering activities to support the utilities cut and cap operations.
  • Conduct vibration monitoring.
  • Conduct continuous air monitoring at project site perimeter while soil disturbance activities are underway.
  • Maintain onsite security for after hours and weekends.
  • Support PSE&G operations in the northern part of the ISS Pilot Study area.

 

Work performed: February 5-9, 2018

 

  • Installed a temporary water treatment system effluent discharge line.
  • Continued to receive deliveries of equipment and materials to the project site.
  • Continued to cut and cap utilities entering the work site area.
  • Conducted vibration monitoring.
  • Conducted continuous air monitoring at project site perimeter while soil disturbance activities were underway.
  • Established onsite security for after hours and weekends.

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>