Monthly Archive: February 2018

Feb 26

Weekly Update 2-26-18

Work to be performed: February 26-March 2, 2018 Continue installation of groundwater treatment system. Continue to receive deliveries of equipment and materials to the project site. Continue to break up underground foundations and structures along the perimeter of the work site area, and remove materials for proper disposal. Continue excavation of soils along the project …

Continue reading »

Feb 20

Weekly Update 2-19-18

Work to be performed: February 20-23, 2018   No work was performed on Monday, February 19 in observance of the Presidents Day holiday.   Continue installation of groundwater treatment system. Continue to receive deliveries of equipment and materials to the project site. Continue to break up underground foundations and structures along the perimeter of the …

Continue reading »

Feb 12

Weekly Update 2-12-18

Work to be performed: February 12-16, 2018   Continue to receive deliveries of equipment and materials to the project site. Continue to cut and cap utilities entering the work site area. Break up underground foundations and structures along the perimeter of the work site area, and remove materials for proper disposal. Perform localized construction dewatering …

Continue reading »

Feb 05

Weekly Update 2-5-18

Work to be performed: February 5-9, 2018 Install a temporary water treatment system effluent discharge line. This work will require the temporary diversion of traffic on the access road south of the ISS Pilot Study project area. We will provide advanced notice prior to its performance. Continue to receive deliveries of equipment and materials to …

Continue reading »